Re-fit works at Refit International, Valencia (status 4 Aug).

Drive train

TaskStatus
Diagnose vibration on electric drive — pulley on combi shaft was misaligned by a few mmDiagnosed
Diagnose June 2026 coupling failure (4 bolts sheared, shaft moved aft ~30 mm)Diagnosed — misalignment
Engineer & install solution — smooth operation at 2300 rpm on electric drive and regen under sailAlignment & coupling done
Test at seaPlanned ~6 Aug / with Steve 9 Sep
Engine room floor paint under electric motor (proper prep)Done
Prop shaft / bearing replacementDone
Shaft brake question — decided not needed; use Yanmar gearbox to stop shaftResolved 18 Jul

Rig, steering & systems

TaskStatus
48 V hi-output alternator — snapped belt, install new belt & tension (410 mm first, 420 mm spare)Done
Main sheet traveler — sheared cheek block, 5 mm bolt sheared flush; remove & re-threadSteve to turn traveler
Rudder shaft play — inspect middle bearing in lazarette; check collar weldsDone
Yanmar full service — impeller, fuel polish filter, razors, fuel filter, oilDone
Genset (Onan) full service — impeller & zincDone
Spinnaker pole Delrin end collar — machine OD 2 mm smallerDone
Lee cloths — starboard cabin & salon couch — fabricate taller/widerDone
Fuel polishing filter + 2 sparesDone
Packout boxes — better support bracket over genset (removable)Status TBD
Laundry-room door in fwd shower — does not latchOpen
Watermaker PEX — replace 2 stiff pieces with PEX-A, leave 2 m spareOpen